Shawano Municipal Airport
Shawano, Wisconsin
Conducted an environmental assessment for a runway extension. Coordinated with Federal, State, and local agencies. Wetland impacts were mitigated. Conducted a public hearing on the preliminary environmental assessment. A Finding of No Significant Impact was obtained. Project was built.
Wittman Regional Airport
Oshkosh, Wisconsin
Conducted an environmental assessment for a new control tower and decommissioning of the existing control tower. Coordinated with Federal, State, and local agencies. A Finding of No Significant Impact was obtained. Project under construction.
Stevens Point Municipal Airport
Stevens Point, Wisconsin
Conducted an environmental assessment for an ILS navigation system, lighting, and taxiways. Coordinated with Federal, State, and local agencies. A Finding of No Significant Impact was obtained. Project in design.