Western Michigan University, Kalamazoo, Michigan
Rebuilt and relocated a pilot paper machine from the west coast to the University. OMNNI provided project management, structural, mechanical and electrical design, electrical controls and process engineering.
UW Parkside Boiler Upgrades
Project included electrical and controls upgrades, and installation of new maintenance monorails supported by the existing structure for two existing boilers.
UW Stevens Point Boiler Upgrades
Project included electrical and controls upgrades, and the removal and replacement of part of the existing roof for installation of a new boiler and economizer. The existing concrete and steel floor was reinforced for the boiler and new support steel was installed for the economizer and stack, as well as modifications to the deaerator platform.